March

Below is a short video about a Public Middle School in Texas. It is worth a look as an example of some of the innovative changes taking place in education. It is also an example of how a building can promote innovative teaching.






January 16, 2013

Links to Three Soil information reports, sent by Jim Brum, from study of Harley site in preparation for excavation and construction
Geo-Tech Report #1
Geo-tech Report #2
Geo-Tech Report #3



January 15, 2013

Suggestions from MAG Creative Workshop - visit with Rachael Baldanza
Suggestions from MAG



January 8, 2013

The official digging of the Chesonis Commons started Monday, January 7th.

landscape.JPG

superwoman.JPGroots.JPG

Caitlin Richard poses on top of one of the tree stumps.............................................Emily Hanss poses in front of the tree roots.

erosion.JPG

Construction workers set up plastic tarp to protect the ground from erosion.

December 14, 2012

New Learning Possibilities from A Shared Learning Site, The Chesonis Commona

When the middle school Design Elective Class attempted to create a hot air balloon that would rise with a self-contained heat system, they were unaware that several weeks before Grade Two students had undertaken a related experiment. Both efforts were successful and instructive for participants, but a key learning opportunity was missed to have the older students mentor the younger ones as well as learn from what they had discovered themselves. The new building space will be the first N-12 workspace in the school. What one class is doing will be continually on display in the large shared workshop area. This will provide Harley with an important new way to integrate learning throughout the grade levels. A capsule view of Grade Two's experiment is below:



November 26, 2012

DSCN3151.JPG
PB Students return to the classroom after the Ground Breaking Ceremony



November 14, 2012

On Tuesday, electrical sub-contractors came and dug a trench for the electrical wires. The previous power supply was under where the foundation of the barn will be and needed to be moved.

men at work.JPG
Electrical sub-contractors

measuring.JPG
Electrical sub-contractors with the architect, Chris Costanza.

feet trench.JPG

ladder trench.JPG
pipes.JPG
Pipes for the electrical wires

pipe trench.JPG



November 13, 2012

2012-11-13_10-40-49_699.jpg
Upper schoolers brave the fall cold to line up on the perimeter of the new building site to provide footage for what will become a video documentary of the building of The Chesonis Commons.
2012-11-13_10-39-01_481.jpg
Max B. captures opening footage for video documenting the stages of erecting the new building.

2012-11-13_10-45-25_396.jpg
Students run the perimeter supplying a bit of action for the video camera.



November 9, 2012

jamir.JPG
The Environmental Science class outlined the perimeter of the barn using stakes and string
emily hit.JPG
Emily Hanss pounds a stake to mark where a corner of the barn will be

string.JPG
Final outline of the barn